Case Study Railroad Switchyard
Polyaromatic Hydrocarbons Chicago , Illinois
Click here for a printable (PDF) version of this document

Site Overview

A locomotive diesel fuel release occurred at an active railroad switchyard.  A subsequent site investigation revealed elevated levels of benzo(a)pyrene ranging from 2.38 mg/kg to 8.2 mg/kg to a depth of 4 feet.  Because of the high rail traffic density at this location, it was not feasible to close the rail spur for remediation.  The BIOX® Process was chosen due to its ability to remediate the area without disrupting site activities.

Project Specifications
 
Contaminant: Benzo(a)pyrene
Contaminated Media: Soil only
Treatment Area:

2,700 square feet
Vertical Extent - 0'- 4'
Total volume - 400 yd³

Project Results

Pretreatment sampling results showed benzo(a)pyrene concentrations ranging from 2.38 mg/kg to 8.25 mg/kg.  The site- specific cleanup objective was established as 0.008 mg/kg.  A single BIOX® treatment event was conducted at the site without disrupting normal activities.  Post treatment samples were collected 34 days after the treatment to evaluate the effectiveness of the remedial activities.  The following table shows the pre- and post-treatment analytical results in mg/kg.

Benzo(a)pyrene (mg/kg)

Location Pretreatment Post Treatment Reduction
SP-1 4.46 <0.008 100%
SP-2 2.38 <0.008 100%
SP-3 8.25 <0.008 100%
SP-4 6.42 <0.008 100%

The published paper for this site is available upon request.